CONSTRUCTION PHOTO GALLERY

AUGUST 2018

These are before and after aerial images of key areas within the GO 10 construction zone. The target date is Dec. 1, 2018 for GO 10 crews to achieve significant completion of structures. Those structures include the bridges and ramps at the I-10/Sunland Park interchange and at the I-10/Mesa interchange.

MAY 2018

The following pictures were captured on Sunday, May 30, 2018.

APRIL 2018

The following pictures were captured on Sunday, April 29, 2018. On this day, a 27-hour closure was in effect, restricting traffic from accessing Sunland Park Drive and all four Sunland Park ramps. The closure was necessary so crews could open the all-new Sunland Park flyover ramp and install a traffic pattern shift at the Sunland Park overpass.

MARCH 2018

FEBRUARY 2018

On Feb. 25, 2018, GO 10 demolished the I-10 Westbound overpass at North Mesa Street (SH 20). Crews also spent the day moving barrier walls and re-striping lanes on I-10 West.

JANUARY 2018

GO 10 expects to make substantial progress on structures at I-10 and Sunland Park in 2018. That means drivers can expect to see some high profile closures at the I-10/ Sunland Park interchange throughout 2018.


Jan. 15, 2018 was the first day of demolition of a 300-foot section of Paisano Drive (US 85). Watch as a piece of concrete rail falls off the edge.

NOVEMBER 2017

For three consecutive Sundays in 2017 – Oct. 29, Nov. 5, and Nov. 12 – GO 10 crews closed I-10 in one direction or the other for 27-hour periods. The first two 27-hour periods were necessary to allow crews to demolish and remove the old Resler Flyover Ramp. The third 27-hour period was necessary so crews could pour bridge deck onto the new I-10 Eastbound overpass at North Mesa Street. These images show the work that took place on Oct. 29.

On Nov. 5, demolition of the Resler ramp resumed, but on the remaining spans over I-10 East.


Crews started jackhammering at 3 am on Oct. 29. By 12:30 pm, the jackhammer’s work was done. You can see more video at https://www.periscope.tv/go10ep/.

AUGUST - OCTOBER 2017

JUNE 2017

The following aerial images were taken June 28, 2017. They show amazing progress and the enormity of the GO 10 project.

MAY 2017

May 2017 Night Images of Beam Setting

On the night of May 30 and 31, 2017, GO 10 crews moved in several girders to be placed alongside the Sunland Park Drive overpass. Operations like this require complete a shutdown of I-10.

APRIL 2017

On April 20, 2017, TxDOT El Paso District held a Work Zone Safety Event featuring the GO 10 project. One of the exhibits on display at the event included the Dragnet safety system, a cable net used by GO 10 crews when they need to close lanes on I-10. The system can stop a semi-truck moving at 65 miles per hour. The event, which took place alongside I-10 near Sunland Park, emphasized the importance of driver attentiveness and patience when driving through work zones.

MARCH 2017

March 12, 2017 Demo Day

On Sunday, March 12, 2017, within a 27-hour period, GO 10 crews demolished the I-10 East Overpass at North Mesa Street and shifted I-10 East traffic lanes onto the newly built I-10 median. The March 12th operation kicked off the second of three phases that will result in the complete replacement of the entire I-10 Overpass at North Mesa.

Wait for it...

March 22, 2017

DECEMBER 2016

These images were taken in December, 2016. Much of the work in December focused on the Resler Flyover Ramp and the I‐10 Overpass at North Mesa Street (SH 20).

NOVEMBER 2016

These images were taken Nov. 4, 2016. New structures can be seen throughout the GO 10 corridor, including new CD lanes, new bridge columns, and new bridges.

OCTOBER 2016

In October 2016, GO 10 crews focused their attention on I-10 at North Mesa Street. They also made significant progress on the westbound collector-distributor (CD) lanes.

AUGUST - SEPTEMBER 2016

The following pictures were taken in August and September of 2016. The images show the construction of several important bridges along I-10 near North Mesa (Exit 11) and near Sunland Park (Exit 13).


Aug. 14, 2016 demolition of the Buena Vista Bridge

GO 10 crews demolished El Paso’s enigmatic Bridge to Nowhere (Buena Vista Bridge) in one Sunday. All I‐10 lanes in both directions were closed and traffic was diverted onto North Mesa Street (SH 20).

JULY 2016

The following pictures were taken in the second half of July where I-10 and US 85 meet (near Sunland Park). These supermen work in 100-plus heat; they work next to hot tar, hot pavement and hot machinery; they work days, nights and Sundays; and alongside fast moving traffic, including 80,000-pound semi-trucks. Give them a “brake.” Please slow down. Drive patiently, courteously, and undistracted.

MARCH 2016

The following pictures were taken on March 18, 2016. The images show a distinct shift in work – a shift from pure earthwork to structural work. In celebration of this milestone, please enjoy these images of new bridge structures and bridge components in the
GO 10 corridor.

JANUARY 2016

Taken Jan. 29, 2016, these images illustrate how workers are often out of the line of sight of drivers, but still only a few feet from highway traffic. GO 10 reminds everyone to give the workers a “brake” and slow down through the work zone.

DECEMBER 2015

The following images were taken Dec. 7, 2015. Work continues to take place behind the concrete barrier between Sunland Park and Executive Center. Much of the work involves earthwork, drainage, bridge widening and electrical components needed for illumination, traffic cameras and dynamic message boards.

GO 10 workers were successful in erecting one of several high mast LED illumination poles on Dec. 1st in the Executive Center area.

OCTOBER 2015

Construction activity on the GO 10 project is well underway. Here are a few scenes from behind the concrete barriers that were taken October 7, 2015.